Home / Case Studies / Second-source end effectors qualified
:: Semiconductor
Second-source end effectors qualified
Problem
An equipment maker depended on a single overseas source with 14-week lead times.
Solution
99.7% alumina end effectors reverse-engineered from drawing, FAIR-style first-article data package.
Result
Qualified in one iteration; lead time cut to 4–6 weeks at materially lower cost.